| SL. NO. | Name of Work | Name of Company | Status | Cost of Project |
|---|---|---|---|---|
| 1 | Feasibility study for Engineering & Traffic Survey of Railway siding for the Orissa Greenfield Project for a 12 MTPA integrated Steel Plant and 1500 MW capacity Power Plant in Keonjhar District, Orissa, in East Coast Rly. |
RITES Limited, Bhubaneswar for M/S ARCELOR Mittal GM/RITES Project office, Bhubaneswar Bhagwan Tower, 1st Floor, Block-A Cuttak Road, Bhubaneswar-751006 |
Completed in 2008 | - |
| 2 | Consultancy service for design, arrangement and layout drawings and preparing Tender schedule and specification for augmentation work of Loco Shed for increasing production to 200 Loco per year. |
Chittaranjan Locomotive Works Chittaranjan, West Bengal. (Indian Railways) CE/ CLW |
Completed in 2008 | - |
| 3 | Preparation of detail design and drawing for Skew slab bridge for a Railway flyover connection with Rail infrastructure at Angul for NALCO in East Coast Railway. |
M/s RITES for NALCO |
Completed in 2009 | Rs. 3.5 Million |
| 4 | Feasibility Report for setting up of a Wagon Factory with Financial viability with detail layout plan & estimate including test of equipments. |
T.I. Metal Forming, Chennai, Chennai – Tiruvellur High Road, Tiruninravur – 602024 |
Completed in 2010 | Rs.5000.0 Million |
| 5 | Preparation of design and drawing for construction of 3x12.2 M clear span PSC slab for railway bridge conforming to DFC loading. East coast Rly. |
M/s ARSS Infrastructure Projects Ltd, |
Completed in 2010 | Rs. 15.0 Million |
| 6 | Consultancy for scheme design, estimate and specification for power supply, Depot layout, Ballast less track for Hyderabad metro consisting of 3 lines having total length of 72 Km. |
M/s Lersen & Toubro Limited, |
Completed in 2010 | This is a pretender consultancy. Cost of Total Metro project was estimated as Rs.1500.0 Billion |
| 7 | Detail Survey and preparation of DPR for setting up an ICD (Integrated container Depot) at Bandamunda. South Eastern Railway. |
M/s Innovative B2B Logistics Solutions Ltd., |
Completed in 2010 | Rs.70.0 Million. |
| 8 | Preparation of DPR with financial viability report for Rail infrastructure at Ranital station of S. E. Railway. |
Sridhi Transport Co. Pvt. Ltd., |
Completed in 2010 | Rs. 74.0 Million |
| 9 | Detail Survey and Technical Feasibility study/Project management services for Rail connectivity work at Container Freight Station, Kolkata. |
M/s Balmer Lawrie |
Completed in 2011 | Rs. 13.4 Million |
| 10 | Final Location survey for construction of new Rly line from Prantik to Suri (33.987Km) and geotechnical investigation etc. for construction of Flyover at Sainthia in connection with doubling from Chinpai to Sainthia. Eastern Railway |
CAO/CON, Eastern Railway |
Completed in 2011 | Rs. 1360 Million |
| 11 | Preliminary Engineering survey for construction of new BG line from Krishnanagar – Nabadwipghat (20km) including survey for fixing of alignment for construction of an important bridge over river Bhagirathi‐ in Eastern Rly. |
CAO/CON, Eastern Railway |
Completed in 2011 | Rs. 800.00 Million |
| 12 | Carrying out Engineering field survey and preparation of Feasibility Report and DPR for a private siding at IKRA in Asansol Division of Eastern Railway. |
M/S Rashmi Cement Ltd. |
Completed in 2011 | Rs. 55.36 Million |
| 13 | Consultancy service for preparation of DPR with financial analysis for setting up a Foundry shop for Railway Wagon / RS items. |
M/s T. I. Metal Forming, Chennai |
Completed in 2011 | Rs. 260.0 Million |
| 14 | Final Location survey and preparation of report for construction of new BG Rly line from Dhaniakhali to Magra, Eastern Railway. |
CAO/CON, Eastern Railway |
Completed in 2012 | |
| 15 | Final Location survey and preparation of report for construction of new BG Rly line from Budge to Pujali, Eastern Railway. |
CAO/CON, Eastern Railway |
Completed in 2012 | |
| 16 | Consultancy Services for preparation of Feasibility report and DPR in connection with modification and remodeling of Private Railway Siding at Sankrail , S.E. Rly |
M/s Ambuja Cement Ltd. |
Completed in 2013 | Rs. 56.0 Million |
| 17 | Feasibility Report & DPR for a private siding connecting KASIA mines from |
ESSEL Mining & Industries Ltd. |
Completed in 2013 | Rs. 447.4 Million |
| 18 | Consultancy for detail Design and drawing for Through Girder span 29.478M for Bridge No.7, span No.5, East Coast Railway |
M/s Rawatsons Engineers Pvt. Ltd. |
Completed in 2013 | Rs. 20.0 Million |
| 19 | Detail survey and preparation of Feasibility report and DPR for additional line in the Durgapur Cement Works siding at Durgapur, including detail Engineering and construction management in Eastern |
M/s Birla Corporation Ltd., |
Completed in 2014 | Rs. 26.26 Million |
| 20 | Consultancy services for survey and preparation of DPR for Common facility work including detail design and drawing at GUA in South Eastern Railway |
M/s Jindal Steel and Power Ltd. |
Completed in 2014 | Rs. 400.0 Million |
| 21 | Consultancy for survey and preparation of DPR for proposed Phase‐1 Railway siding extension of Birarajpur station in Chakradharpur Division of South Eastern Railway. |
Adhunik Power & Natural Resources Ltd. |
Completed in 2015 | Rs. 30.0 Million |
| 22 | Consultancy for detail survey and preparation of DPR for proposed PFT at Kalunga in CKP Div of South Eastern Railway |
Sri Mahabir Ferro Alloys Pvt. Ltd. |
Completed in 2015 | Rs. 28.0 Million |
| 23 | Consultancy service for the proposed Two spur unloading siding of HPCL at Budge Budge in Sealdah Division of Eastern Railway. Detail survey and preparation of DPR. |
Hindustan Petroleum |
Completed in 2015 | Rs. 74.1 Million |
| 24 | Detail Engineering survey and preparation of DPR and Project Management Services for setting up Railway tank wagon siding at IOCL’s Paradeep Lighterage Terminal, Paradeep (Orissa). East Coast Rly, Indian Railway. |
Indian oil Coorporation Ltd. Engineering Department,, 6th Floor, Indian Oil Bhawan,g-9, Ali Yavar Yang, Bandra (East), Mumbai-400 051. India. |
Completed in 2015 | 68.6 Millions |
| 25 | Detail survey and preparation of Feasibility report and DPR for Private Freight Terminal at Gobra in Eastern Railway |
M/s SFA Logistics Park Pvt. Ltd. |
Completed in 2016 | Rs. 1500.0 Million |
| 26 | Project Management consultancy for construction and commissioning of siding at Andal under Eastern Railway. |
M/s Birla Corporation Ltd. |
Completed in 2016 | Rs. 40.0 Million |
| 27 | Consultancy services for survey and preparation of Feasibility Report, DPR, Detail Engineer, and Project Management & Supervision. |
M/s JSW Cement Ltd. |
Completed in 2017 | Rs. 300.0 Million |
| 28 | Consultancy services for preparation of detail survey, Feasibility Report and DPR for construction of Brown field PFT at Nipania under Raipur Division of South East Central Railway. |
M/s Suman Forwarding Agency, |
Completed in 2017 | Rs. 60.0 Million |
| 29 | Consultancy for survey & preparation of Feasibility Report, DPR, ESP for Railway siding at Barajamda of South Eastern Railway. |
M/s Deepak Steel & Power Ltd. |
Completed in 2018 | Rs. 40.0 Million |
| 30 | Certification of Track & Bridges of private Railway siding of M/s TATA Steel at JODA (East) JMTC siding between Murga Mahadev Road and Banspani, Chakradhapur Division of South Eastern Railway for 25 Axle Load. |
M/s E to E Transportation Infrastructure Pvt. Ltd. |
Completed I n 2018 | |
| 31 | Consultancy for proposed modification to Private Railway siding at Nimpura - Gokulpur and conversion to PFT in South Eastern Railway |
M/S Rashmi Cement Ltd. |
Completed in 2018 | Rs. 25.8 Million |
| 32 | Modification of existing Siding of SAIL at Meghahatuburu in South Eastern Railway for provision of EIMWB. |
STEEL AUTHORITY OF INDIA LTD. (A Govt. of India Undertaking) Raw Material Division, Meghahatuburu Iron Ore Mine, Dist- Singhbhum (West), Jharkhand-833223. |
Completed in 2018 | Rs. 10.0 Millions |
| 33 | MEP Design consultancy works of Central Park Depot of East-West Metro for KMRCL project at Kolkata consisting of detail design of Electric lighting, Air Conditioning and Ventilation, Fire Fighting, Water Supply and Diagram scheme for Central Depot of Metro Railway |
M/s Consolidated Construction Consortium Ltd.( CCCL), Chennai. |
Completed in 2018 | 1560.0 millions |
| 34 | Consultancy work for Project Management & construction supervision and preparation of revised estimates, Completion drawings, Siding Agreement, Land Licensing Agreement and execution of the same, for Rungta Mines siding between Jaroli-Nayagarh under South Eastern Railway. |
M/s Rungta Mines Limited Jaiang Iroin & Manganese Mines, Keonjhar, -758052 State- Odisha. |
Completed In 2018 | Rs.25.8 millions |
| 35 | Consultancy for survey, preparation of Feasibility Report, DPR,, Detail Engineering, BOQ, Tender documents for modification/augmentation of the existing siding of TATA Metaliks at Gokulpur in Kharagpur Division of South Eastern Railway. |
TATA Metaliks Limited Vill-Mahespur, PO-Samraipur Kharagpur, West Bengal-721 301 |
Completed in 2018 | 103.4 millions |
| 36 | Consultancy services of Mechanical Workshop, Samastipur for augmentation of manufacture of BOXNHL MBS wagon, East Central Railway |
Chief Workshop Manager |
Completed in October,2019 | Rs.103.35 crores. |
| 37 | Consultancy for preparation Feasibility report, DPR, Detail design, Preparation of OHE layout & Signaling layout and Land Licensing Plan for development of private siding at Nimpura- Gokkulpur under South Eastern Railway. |
M/s Orissa Metaliks Pvt Ltd. |
Completed in 2020 | Rs. 56.9 Millions |
| 38 | Consultancy for preparation Feasibility report, DPR, Detail design, Preparation of OHE layout & Signalling layout and Land Licensing Plan for development of private siding at Nimpura – Gokulpur under South Eastern Railway |
M/S Orissa Manganese and Power Ltd. 1, Grastin Place, ORBIT House, 3rd floor, Room No.3B, Kolkata-700001 |
Completed in 2020 | Rs.56.9 Millions |
| 39 | Consultancy for survey, preparation of Feasibility Report and DPR and approval from Railway for development of a Coal Loading siding of WBPDCL at Panchra |
WBPCDL, Bidyut Unnayan Bhavan, 3/C Block –LA, Secrtor-3 Salt lake City, Kolkata -7000106 West Bengal. |
Completed in 2020 | 10.50 lakhs |
| 40 | Consultancy for survey, preparation of Feasibility Report and DPR and approval from Railway for Time Motion Study of Railway siding for 2x600 MW ATPP, Anuppur (MP). | MB Power (Madhya Pradesh) Ltd. 239, Okhla Industrial Estate, Phase-3, New Delhi-110020 |
Completed in 2021 | |
| 41 | Consultancy Services for survey and preparation of Feasibility report and DPR for augmentation of existing BRMS siding of M/s Bisra Stone Lime Company Ltd. Birmitrapur, in Chakradharpur Division of S. E. Railway. |
The Bisra Stone Lime Company Ltd. ( A Govt. of India Enterprise), Birmitrapur, Sundargarh, Odisha |
Completed in 2021 | RS. 8 Lakhs |
| 42 | Independent Engineer for Chattisgarh East West Railway Ltd (CEWRL) for Gevra Rd to Pendra Rd (Double Line) Km 0.0 to Km.11.51 Urga to Kushmunda (Single Line) plus 44.654 Km long connectivity(including Kushmunda, Junadihm Dipka, Saraipali, Kartali, Ambika & Vijaya West (Single Line) | Chattisgarh East-West Railway Limited, (A Govt of. India Undertaking) 2nd flor, CSIDC Commercial Complex, Mahadev Ghat Road, Raipura Chowk, Raipur (C.G) – 492013. | Completed in 2022 | 103.4 millions |
| 43 | Preparation of Feasibility report and DPR with detail design for Uniflow MGR system for loading siding of NMDC at Kirandul.Chhatisgarh, in East Coast Railway. | National Mineral Development Corporation, Khanij Bhawan, Castle Hills, Hyderabad – 500 028 | Completed in 2022 | 6237.64 lakhs |
| 44 | Consultancy for preparation of ESP and Project Detail for proposed siding at Jakpur Station of Kharagpur Division in South Eastern Railway | M/s. Orissa Alloy Steel Pvt Ltd, 1, Garstin Place, ORBIT House, Kolkata – 700001 | Completed in 2022 | 50 Crore |
| 45 | Proposed GCT terminal for M/s Times Steel and Power Private Limited taking off from Kalunga Station of Chakradharpur Division in S.E.Railway. Detail survey, DPR, ESP, Detailed Engineering. |
M/s. Time Steel and Power Private Limited., Dua Complex Panposh Road,Rourkella – 769004 Odisha. |
Completed in 2022 | 23 Crore |
| 46 | Consultancy for Techno Economic Feasibility report for production of Manufacture spares for Railway Wagons & Coaches. | M/s. Maxlux Glass Pvt Ltd., |
Completed in 2022 | 16 Crore |
| 47 | Consultancy for detail design & drawing in Ballast less track at Silo Area at NTPC/KahalgaonNTPC Limited, Kahalgaon Super Thermal Power project Bhagalpur, Bihar. | NTPC Limited, Kahalgaon Super Thermal Power project Bhagalpur, Bihar. |
Completed in 2022 | 50 Lakhs |
| 48 | Pre-Bid Engineering Consultancy Services for Construction of New Broad Gauge Rly line between Ch.8.020 & Ch.l 48.000 including Rly Electrification, S&T works and Genl Elec Services between Koteganguru(Excl) & Shikaripura(Incl) stations in Shivamogga Shikaripura-Ranebennur New Line Project in the S.W.Rly | HGIEL, 14, Panchavati Colony, Ratanada, Jodhpur- 342001 | Completed in 2022 | 450 Crore |
| 49 | Pre-Bid Engineering Consultancy Services for Construction and Commissioning of Chandigarh-Baddi New Broad Gauge Rly Line ( 30.295 Km Ch. 2219 m to 28076m ) including Electrification and S&T Works on EPC Mode. | HGIEL, 14, Panchavati Colony, Ratanada, Jodhpur- 342001 | Completed in 2022 | 397 Crore |
| 50 | Pre-bid consultancy services for Construction of new BG Railway Line Project from Murkongselek station in the state of Assam (Ch:0.780 Km) to prosed Pasighat station in the state of Arunachal Pradesh (Ch: 27.062 Km) including Electrical (General), Signal & Telecommunication works” | SCL Infratech Limited |
Completed in 2022 | 402 Crore |
| 51 | Construction of Gati Shakti Multi Modal Cargo Terminal entirely on Railway Land at Sankrail Goods Terminal Yard (SGTY). Howrah | M/s. Balmer Lawrie & Co Ltd, 21, |
Completed in 2022 | 12 Crore |
| 52 | Consultancy for detail survey, preparation of DPR, ESP, GAD, Engineering details and approval from Railway . Project Management Consultancy for Railway Siding Works at Kalaburagi Depot, Karnataka. Taking Off from Hirenanduru Station of Sholapur Division of Central Railway. | Bharat Petroleum Corporation Ltd, “A” Installation Sewree Fort Road, Sewree (East), Mumbai- 400015 |
Completed in 2023 | 52.0 crores. |
| 53 | Engagement of Consultant for Designing and PMC (Project Management Consultancy) Services for Refuishment of Railway Siding and Open Yard at WD SONAPUR, KOLKATA, Shyama Prasad Mukherjee Port, Eastern Railway. | M/s. Balmer Lawrie & Co Ltd, 21, |
Completed in 2023 | 7.0 crores |
| 54 | Consultancy for development of Gati Shakti Terminal at Baihata Railway station in N. F. Railway for new private siding in the name of B.R. Transcon LTD. | B. R. Transcon Limited |
Completed in 2023 | 20.0 Crores |
| 55 | Consultancy for S&T works at Hot Metal Track at TATA Steel, Kalinganagar, East Coast Railway which include Preparation of SIP, DPR, Scheme Design, Route Control Chart (RCC), Cable Core Plan, Cable Route Plan, Cable Termination Plan, Power supply scheme, Track bonding plan, Circuit Diagram, BOQ & Specification, Detailed estimate, Construction & Supervision & As built drawing. | TATA Steel Limited |
Completed in 2023 | 57 Crores |
| 56 | Consultancy for survey of 150.0 acre of land, preparation of FSR, DPR and construction supervision for setting up of railway siding in Texmaco Rail land adjacent to Sankrail Railway station of South Eastern Railway. | Texmaco Rail & Engineering Ltd. |
Completed in 2023 | 82 Crores |
| 57 | Consultancy for site survey, study of existing system of operation, development of concept plan, study of OHE and S&T requirement, preparation of estimate, preparation of Feasibility Report for proposed Goods Shed, siding for loading of Coal near Kurwa Railway Station in Dumka – Rampurhat line of Howrah Division in Eastern Railway and approval from Railway, including Detail design and Construction Supervision. | BGR Mining & Infra Ltd., |
Completed in 2023 | 38 Crores |
| 58 | Setting up of a proposed Gati Shakti Multi Modal Cargo Terminal taking off from BERO Station in ADRA Division of South Eastern Railway. | Captain Steel India Ltd. |
Completed in 2023 | 47 Crores |
| 59 | Consultancy for survey, preparation of Feasibility Report, DPR and approval from Railway including Project Management for Railway Siding from Baktarnagar – Andal Link Line under Asansol Division of Eastern Railway. | Howrah Gases Limited |
Completed in 2023 | 14 Crores |
| 60 | Conducting Final Location Survey, Traffic Survey, submission of comprehensive DPR for all Civil, Electrical and S&T work, preparation of detail estimate along with Alignment Plan, Yard Plan, drawing for minor bridges, major bridges, ROB/RUB, FOB, Level Crossing drawings, Hydrological & Geotechnical Investigation and all other ancillary works at following locations: (i) Bypass line at Rupsa (Kharagpur to Baripada) (Item No. 33) (10 km), (ii) Flyover from Rakha Mines to Asanboni up line to joint line (5 km), (iii)Flyover from Panskura east outer (Raghunathbari end) to Panskura (5 km) under the jurisdiction of CPM/GSU/KGP of South Eastern Railway. | South Eastern Railway, |
Completed in 2024 | 1800 Crores |
| 61 | Construction of all civil works for extension of private Railway siding within Railway land at Birarajpur station in Chakradharpur. The work consisted of earthwork in formation, blanketing, concrete work in retaining wall, drains and Construction of Railway Under bridge. The work also included procurement of ballast, P.way material along with laying and linking of track Including commissioning. | M/s Adhunik Power & Natural Resources Ltd. |
Completed in 2016 | |
| 62 | Construction of all civil works for augmentation of Private Railway siding of Birla Corporation Limited. The work consisted of earthwork in formation, blanketing, bridge construction RCC 3x6.1m, laying of track and commissioning the same along with inter locking signalling works. The work also included OHE and power supply work required for electrification of the yard. | M/s Birla Corporation Ltd. |
Completed in 2017 | |
| 63 | Supply & erection of 25 KV Over Head Electrification & Switching station for private Siding of M/s JSW Cement Ltd. including Block station between Godapiasal & Salboni, Adra Division of South Eastern Railway. Full Electrification works for a new Railway siding of JSW Cement at Salboni, Medinipur Dist. Of West Bengal. | M/s JSW Cement Ltd. |
Completed in 2018 | |
| 64 | Consultancy and construction work for a private railway siding of IOCL at Haldia, West Bengal Turn key work of preparation of DPR report, detail drawings for construction of Private Railway Siding involving formation, blanketing, track work etc. at Haldia in West Bengal for IOCL project at Haldia under principal Contractor L&T. | M/s. L&T |
Completed in 2019 | 4.3 Crores |
| 65 | Maintenance of Track for 2 years, 2021-22 & 2022-23 |
M/s IOCL, Haldia Refinary |
Completed in 2023 | 1 Crore |
| 66 | Provision of OHE in connection with capacity enhancement at Barharwa Railway siding |
Sr.DEE(TRD) Eastern Railway, Malda | Completed in 2024 | 1.25 Crore |
| 67 | Track Maintenance, Miscellaneous P.Way(Zonal)/ Track works for the period from 01.10.2022 to 30.09.2024 in the section of SSE/P.Way/GII under the jurisdiction of ADEN/JHARGRAM. | South Eastern Railway ,Kharagpur division-Engg, |
Completed in 2024 | 1.04 Crore |
| 68 | Miscellaneous P.Way(Zonal)/ Track works for the period from 01.10.2022 to 30.09.2024 in the section of SSE/P.Way/JGM under the jurisdiction of ADEN/JHARGRAM. | South Eastern Railway , |
Completed in 2024 | 0.82 Crore |